ADU & Garage Conversion · Permitting Close-Out
Certificate of Occupancy or Final Inspection: What Actually Closes Out Your Permit

Houston calls its sign-off document a Certificate of Occupancy. Harris County calls its own version a Certificate of Compliance — a different name for unincorporated-area permits. Here is what each office’s own published material actually says about closing out an ADU or garage-conversion rental-unit permit, and what it honestly does not say.

Book a ConsultationCall (832) 532-6829
PERMITInspections passedFire Marshal (if required)COCertificate ofComplianceHarris County’s term foran unincorporated-area permit
Compliance
Harris County Engineering’s own term for its sign-off document — not "Occupancy." Source: oce.harriscountytx.gov/Services/Permits/FAQ, checked Oct. 12, 2026.
$260
Harris County’s fee for each re-inspection after the first (the first inspection and first re-inspection are included in the original permit fee).
Commercial
The scope Houston’s own Certificate of Occupancy page states for itself — it does not address 1-2 family dwellings, ADUs, or garage conversions.

Sources: oce.harriscountytx.gov/Services/Permits/FAQ and houstonpermittingcenter.org/building-code-enforcement/occupancy-inspections. Checked Oct. 12, 2026.

Two offices, two different sign-off documents

Which office has jurisdiction over your ADU or garage-conversion rental unit — the City of Houston or Harris County Engineering — determines not just which permit you pull, but what document (if any) closes it out and what it is called. The two offices do not use the same term, and neither one’s own published material addresses a residential accessory structure the same way it addresses a commercial building.

If you have not yet confirmed which office applies to your property, MAV’s companion guide covers exactly that question: Houston Permitting Center vs. Harris County Engineering. This guide picks up from there — once you know which office applies, here is what finishes the permit.

City of Houston (incorporated)Harris County Engineering (unincorporated)
Document nameCertificate of Occupancy — per the city’s own page, scoped to commercial buildingsCertificate of Compliance
What triggers itA commercial building or lease space being occupied, or an occupancy-classification change with new approved plans/permitsA valid permit with all required inspections completed and passed; a Fire Marshal inspection for fire-code projects
Residential ADU / garage conversionNot addressed by the city’s own CO page — the permit’s own final-inspection approval is what is documented as closing it outIssued by the Harris County Permit Office once required inspections (and the Fire Marshal inspection, if applicable) are approved
How you request itInspections tracked via the PDI system by project number; contact Occupancy Inspections for CO mattersEmail Development Inspection to request the Fire Marshal inspection; email Compliance to request the Certificate of Compliance
Re-inspection costNot stated in the city’s published material for a residential projectFirst inspection + first re-inspection included in permit fee; $260 per re-inspection after that
Interactive check
Which process applies to your project?

Pick what’s closest to your ADU or garage-conversion rental unit:

Your permit runs through the Houston Permitting Center. The city’s own Certificate of Occupancy page is scoped to commercial buildings and does not address a residential accessory structure directly — what IS documented is that inspections are scheduled and tracked through the PDI system, and the permit closes out once its required inspections are approved. Confirm with the Houston Permitting Center whether any additional document applies to your specific project.
Your permit runs through Harris County Engineering. Per the county’s own Permits FAQ, you need a valid permit with all required inspections completed and passed; the Harris County Permit Office issues a Certificate of Compliance (not “Occupancy”) once that is confirmed — and, for fire-code projects, once a requested Fire Marshal inspection is approved.
That is the first question to answer — see MAV’s companion guide, Houston Permitting Center vs. Harris County Engineering, or ask MAV to confirm it as part of your project’s permitting.
In Harris County, your first re-inspection is included in the original permit fee — every one after that is $260. The city’s own published material does not state a comparable Houston-side figure; ask the Houston Permitting Center directly for your project’s fee schedule.

Summarizes each office’s own published material as of October 2026; not a substitute for confirming your specific project directly with the permitting office or MAV.

What each office’s own material actually says

Both quotes below are taken directly from each office’s own current web page, checked Oct. 12, 2026 — not from a secondary summary.

City of Houston Permit → required inspections scheduled via the PDI system → inspections pass → permit closes out on final approval. City’s own CO page scopes itself to commercial buildings — not 1-2 family/ADU Harris County (unincorporated) Permit → all required inspections pass → Fire Marshal inspection approved (fire-code projects) → request by email. Document issued: “Certificate of Compliance” — not “Occupancy”
Illustration. A simplified comparison of what closes out a City of Houston permit versus a Harris County permit for the same kind of project.
Harris County re-inspection fee, per the county’s own Permits FAQ
First inspection + first re-inspection: 0 $First inspection + first re-inspection0 $Each re-inspection after that: 260 $Each re-inspection after that260 $
+View as table
ItemValue ($)
First inspection + first re-inspection0
Each re-inspection after that260

Source: Harris County Engineering, Permits FAQ (oce.harriscountytx.gov/Services/Permits/FAQ). Checked Oct. 12, 2026.

Harris County: "Certificate of Compliance"
The Permits FAQ states: a Certificate of Compliance requires “a valid permit with all required inspections completed and passed.” For fire-code projects, the Fire Marshal performs the final inspection, requested by emailing Development Inspection; the Harris County Permit Office then issues the Certificate of Compliance once that inspection is approved and a request is emailed to Compliance.
Harris County: re-inspection fees
The FAQ states plainly: “The first inspection and first re-inspection fee is included in the original permit fee. Subsequent re-inspection fees are assessed at $260 each.”
Houston: Certificate of Occupancy scope
The city’s Occupancy Inspections page states a CO is needed before “a commercial building or an individual lease space within a commercial building” is occupied, or when an occupancy classification changes with new approved plans. One- and two-family dwellings, ADUs, and garage conversions are not addressed in that page’s content.
Houston: how inspections are tracked
The Houston Permitting Center provides a Check Inspection Status tool (via its PDI system) referenced by an 8-digit project number — the mechanism that governs scheduling and closing out any building-permit inspection, residential or commercial.

How a close-out actually comes together

  1. 1
    Confirm
    Confirm which office has jurisdiction
    Houston’s incorporated city limits route to the Houston Permitting Center; unincorporated Harris County routes to Harris County Engineering. See MAV’s companion guide if this isn’t already clear for your property.
  2. 2
    Build
    Build to the approved permit
    Construction begins once permits are obtained — Harris County’s FAQ states this directly; the same principle governs City of Houston permits.
  3. 3
    Schedule
    Schedule required inspections
    Houston: tracked via the PDI system by project number. Harris County: email Development Inspection to request a Fire Marshal inspection on fire-code projects.
  4. 4
    Pass
    Pass every required inspection
    A Harris County Certificate of Compliance explicitly requires ALL required inspections completed and passed — not just the final one. Budget for the possibility of a re-inspection (Harris County: $260 after the first free one).
  5. 5
    Close out
    Close out the permit
    Houston: the permit closes out on final-inspection approval through PDI. Harris County: email Compliance to request the Certificate of Compliance once the Fire Marshal inspection (if applicable) is approved.
Garage conversion
Every inspection on the permit has to pass before the project closes out — not just the last one.
Detached ADU
Whether a Fire Marshal inspection applies in Harris County depends on how the project is classified.
Attached ADU
The same close-out question applies whether the unit is attached or detached.
Converted garageClose-out checklist□ All inspections passed□ Fire Marshal (if applicable)□ Document requested
Illustration. A garage-conversion floor plan alongside the close-out checklist each permit has to clear before it is finished.
Accessory dwelling unitSame two questionsWhich office has jurisdiction?What document (if any) closesthe permit out?
Illustration. A detached-ADU floor plan — the same jurisdiction and close-out questions apply whether the unit is attached, detached, or a converted garage.
Questions to ask before you call a project finished

Tick each one off as your contractor answers it.

Based on each office’s own published material as of October 2026. Always confirm your specific project’s requirements directly with the permitting office.

What MAV ADU clients say on Google5.0on Google

Verified Google reviews from MAV ADU-construction clients, plus one general design-build review labeled “across our services” — no garage-conversion-specific review exists in the verified set yet.

“I had a great experience with Mav building my ADU. The entire process was smooth, professional, and much easier than I expected. Their team was responsive, transparent, and kept me informed every step of the way.”

Omer Ahmed · Google review

“Just completed my ADU with MAV great experience from start to finish highly recommend working with shon very professional”

Sam Nogroski · Google review

“Really pleased with my experience with MAV Design & Build. They were professional, easy to work with, and did a great job with the project.”

Sebastian Gonzalez · Google review
Read all reviews on Google →

About MAV Design & Build

Veteran-owned
Licensed and insured Houston design-build contractor, with a 5-year workmanship warranty on every completed project.
ADU & garage conversion
Design-build ADU construction and garage-to-living-space conversions across the Houston area, including permitting coordination.

Frequently asked questions

Does a residential ADU or garage conversion get a "Certificate of Occupancy" in the City of Houston?+
Houston’s own Occupancy Inspections page scopes its Certificate of Occupancy requirement to commercial buildings and individual commercial lease spaces — it does not address one- and two-family dwellings, accessory dwelling units, or garage conversions anywhere in its published content. What IS documented for a residential building permit is the inspection process itself: inspections are scheduled and tracked through the city’s PDI system by an 8-digit project number, and the permit closes out once its required inspections are approved. Whether the city issues any separate document for a residential accessory structure beyond that final-inspection approval is not stated on its own site — confirm directly with the Houston Permitting Center for your specific project.
What is a "Certificate of Compliance," and how is it different from a Certificate of Occupancy?+
Certificate of Compliance is Harris County Engineering’s own term — not Houston’s “Certificate of Occupancy” — for the document it issues on unincorporated-area permits. Per the county’s own Permits FAQ, obtaining one requires “a valid permit with all required inspections completed and passed,” plus (for fire-code projects) a Fire Marshal inspection requested by email; the Harris County Permit Office then issues the Certificate of Compliance once that inspection is approved.
Does an ADU or garage-conversion rental unit count as a "fire code project" in Harris County?+
Harris County’s Permits FAQ scopes its Fire Marshal final-inspection requirement to “Fire Code Projects” without defining, in the material it publishes, which residential project types fall into that category. Rather than guess, confirm this directly with Harris County’s Development Inspection office (or ask MAV to confirm it as part of your permit) before assuming either way.
What does a re-inspection cost in Harris County if the first one doesn’t pass?+
The first inspection and the first re-inspection are included in the original Harris County permit fee. Every re-inspection after that is billed separately — $260 each, per the county’s own fee schedule.
Who do I contact to schedule an inspection?+
For a City of Houston permit, inspections are scheduled and their status tracked through the Houston Permitting Center’s PDI (project inspection) system, referenced by your permit’s 8-digit project number. For a Harris County permit, Harris County’s Permits FAQ directs fire-code-project applicants to email Development Inspection to request the Fire Marshal inspection, and Compliance to request the Certificate of Compliance once that inspection is approved. MAV manages this scheduling as part of its design-build process either way.
How do I know whether my project falls under the City of Houston or Harris County?+
That is a different question from this guide’s topic — see MAV’s companion guide, Houston Permitting Center vs. Harris County Engineering, which walks through how to tell which office has jurisdiction over a given property.

Planning an ADU or garage conversion in Houston?

MAV confirms which office has jurisdiction over your property, manages the inspection schedule, and tells you exactly what closes your permit out — before you assume it’s finished.

Book a ConsultationCall (832) 532-6829

For ADU design and construction, see MAV’s ADU construction hub. For garage conversions, see MAV’s garage conversion hub and the garage conversion ADU guide. For which office has jurisdiction over your property, see Houston Permitting Center vs. Harris County Engineering. Final inspection also covers the garage’s fire-rated separation and the smoke/CO alarm placement a conversion triggers — see MAV’s guide to garage conversion fire separation, smoke & CO alarm requirements. Once your permit closes out, see MAV’s guide to property taxes and appraisal after an addition in Texas. If this is a conversion that was never permitted in the first place, see MAV’s guide to unpermitted garage conversion disclosure & risk.

Sources
  1. Harris County Engineering, Office of the County Engineer — Permits FAQ
  2. Harris County Engineering Permits Office — Fee Schedule (re-inspection fees)
  3. Houston Permitting Center — Occupancy Inspections (Certificate of Occupancy)
  4. Houston Permitting Center — homepage / inspection-status tools
  5. MAV Design & Build: Houston Permitting Center vs. Harris County Engineering
  6. MAV Design & Build: ADU Construction
  7. MAV Design & Build: Garage Conversions

Two residential-specific Houston Permitting Center URLs returned HTTP 404 during this research and were not substituted with an assumed fact; the city’s own Certificate of Occupancy page’s commercial-only scope is disclosed above rather than extended to residential ADUs/garage conversions by assumption. Checked October 12, 2026.

What Houston Homeowners Say⭐ 5.0  •  Google Reviews
Waseem NaqviApril 2026
★★★★★

I'm extremely satisfied with my kitchen renovation. The entire process was handled with professionalism and precision. The crew was respectful, efficient, and always made sure I was informed every step of the way. The final result — a beautiful, well-designed kitchen with top-quality finishes and excellent craftsmanship.

AviadApril 2026
★★★★★

Love their work, the kitchen turned out amazing and exceeded our expectations. Completed in much shorter time than I thought it would. Can't recommend them enough!!

Dwight HoldenMarch 2026
★★★★★

Great experience working with this company! They remodeled my kitchen and did an amazing job. The team was professional, easy to work with, and always on time. Everything went smoothly, and they paid attention to the small details.