It can be, but check three Dickinson rules before running the numbers. The city’s Unified Development Code allows one ADU per lot of up to 600 square feet in its RE, NC and GR districts, and the owner must live on the property. New residential construction in a mapped flood area must have its lowest floor at least 18 inches above base flood elevation, and a flood-insurance premium may apply. We did not find a sourced Dickinson rent figure, so this page quotes no income or break-even numbers. MAV checks your zoning district and flood zone before design.
The investment question here is mostly a flood-zone question. Dickinson’s Unified Development Code (Article V, Sec. 18-30, read 2026-11-05) requires a floodplain development permit and, in mapped flood areas, a lowest floor at least 18 inches above base flood elevation for new residential construction and substantial improvement. If the property is in a mapped Special Flood Hazard Area, expect an ongoing flood-insurance premium on top of construction cost; the premium depends on your insurer and elevation certificate, so MAV does not quote one. MAV checks the property’s flood-zone designation and builds these factors into the plan during the free 3D design phase. See our full FEMA flood-elevation guide for Houston-area additions and ADUs.
Building an ADU in Dickinson, TX: who issues the permit
Who issues the permit: Dickinson is an incorporated city in Galveston County. For a property inside city limits, permits, plan review and inspections go through the City of Dickinson Building Permits & Inspections Division (Community Development, City Hall, 4403 Highway 3; 281-337-6259; Monday to Thursday 7:30 a.m.–5:30 p.m., Friday 7:30 a.m.–11:30 a.m.). Applications, plans, review comments, fees and inspections run through the city’s MyGov portal. The city’s building page says it adopted the 2024 ICC codes and the 2023 National Electrical Code with amendments (Ordinance 2110-2026). If your address is outside city limits, confirm which authority applies before design starts.
What the city code says (Dickinson Unified Development Code, Chapter 18, read from the city’s enCodePlus library on 2026-11-05; the UDC took effect August 14, 2024):
- Sec. 18-15(b)(1) Accessory dwelling unit: permitted in the Rural and Estate (RE), Neighborhood Conservation (NC) and General Residential (GR) districts; one ADU per lot; no more than 600 square feet; located to the side or rear of the principal building; one extra parking space for the ADU; the property owner must live on the property in the principal structure or the ADU; no more than one residential electric, water and gas meter per lot; same address as the principal residence. The code illustrates attached, above-garage, converted-garage and detached ADUs.
- Sec. 18-15(a) general accessory-structure rules: detached accessory structures need at least 5 feet from interior side and rear lot lines (corner setbacks follow the main building); they sit behind the front facade of the principal structure; they may not encroach into an easement; and they must be subordinate in height to the principal structure. Trailers, containers and similar structures may not be used as accessory buildings.
- Article V, Sec. 18-30 (flood hazard reduction): the city adopts FEMA’s Flood Insurance Study for Galveston County and its maps dated August 15, 2019; a floodplain development permit is required; in mapped flood areas new residential construction and substantial improvement must have the lowest floor at least 18 inches above base flood elevation; in Zone X (shaded) at least 18 inches above the highest adjacent grade (or 6 inches above the street crown where the street carries floodwater); enclosures below the flood elevation are limited to parking, access and storage, with a non-conversion agreement filed with the deed.
What that means for planning: an ADU in Dickinson has a published size cap and an owner-occupancy condition, and a lot’s flood zone can change the foundation and floor height. Whether your lot is in an RE, NC or GR district, how the Urban Transition, Downtown and Mixed-Use districts treat ADUs, lot-coverage limits, any rental-registration or short-term-rental rule, and residential plan-review times are not verified: MAV confirms them with Community Development before drawings are finalized. Private deed restrictions or an HOA can add further limits.
Sources: City of Dickinson Building Permits & Inspections · Dickinson MyGov portal · Ordinance 2110-2026 (building codes) · Unified Development Code, Ch. 18 (enCodePlus). Compare other cities in MAV’s ADU permits by neighborhood guide.
Dickinson TX Cost Guide
Our Process in Dickinson TX
What We Build for Dickinson TX Homeowners
What We Build for Dickinson TX Homeowners
Dickinson ADU Questions
Who issues ADU permits in Dickinson, TX?
For a property inside Dickinson city limits, permits go through the City of Dickinson Building Permits & Inspections Division, part of Community Development, at City Hall (4403 Highway 3; 281-337-6259; Monday to Thursday 7:30 a.m. to 5:30 p.m., Friday 7:30 a.m. to 11:30 a.m.). Applications, plan uploads, review comments, fees and inspections run through the city’s MyGov online portal. The city’s building page says it adopted the 2024 ICC codes and the 2023 National Electrical Code with amendments (Ordinance 2110-2026). MAV prepares and files the permit set and confirms that your address is inside city limits before design begins.
Can I build an ADU in Dickinson, TX, and how big can it be?
Yes, in some districts. Sec. 18-15(b)(1) of the Dickinson Unified Development Code (effective 8/14/2024) permits accessory dwelling units in the Rural and Estate (RE), Neighborhood Conservation (NC) and General Residential (GR) districts: one ADU per lot, no larger than 600 square feet, located to the side or rear of the principal building, with one parking space for the ADU in addition to the main house’s spaces. The code names four forms: attached, above-garage, converted-garage and detached. Whether your lot is in one of those districts, and the rules for other districts such as Urban Transition, Downtown or Mixed-Use, are not verified here; MAV checks your zoning district first.
Can I rent out an ADU in Dickinson, TX?
The code requires the property owner to live on the property, either in the main house or in the ADU (Sec. 18-15(b)(1)(vi)), and allows no more than one electric, water and gas meter per lot. We did not find a rental-registration or short-term-rental rule in the sections we read, so that part is not verified, and this page does not quote a rent or break-even figure because no sourced Dickinson rent data was verified. Confirm the planned use with Community Development before design begins.
How do Dickinson flood rules affect an ADU?
Dickinson adopted FEMA’s Flood Insurance Study for Galveston County (August 15, 2019) and its flood maps in Article V of the code. A floodplain development permit is required, and in mapped flood areas new residential construction and substantial improvement must have the lowest floor at least 18 inches above base flood elevation (Sec. 18-30). In Zone X (shaded) the lowest floor must be at least 18 inches above the highest adjacent grade, or six inches above the crown of the street if that is greater and the street is in the path of water egress. Enclosures below the flood elevation may be used only for parking, building access or storage, with a non-conversion agreement filed with the deed. Flood-insurance cost depends on your insurer and elevation certificate, so MAV does not quote a premium.
How long does ADU permitting and construction take in Dickinson, TX?
The City of Dickinson pages we read do not publish a review time for residential plans, so a firm number would be a guess (not verified). A typical MAV project runs from a free in-home consultation and 3D design preview through feasibility, permit filing, construction and the final inspection, and MAV puts a written schedule in every proposal once the permit path for your address is confirmed.
Recent MAV ADU Projects
A few finished MAV accessory-dwelling-unit projects from our Houston-area portfolio.



More ADU Resources from MAV
Compare permitting rules across nearby cities in our ADU permits by neighborhood guide, explore ADU floor plans and layouts, or review ADU financing options in Texas. See our full ADU construction services overview, or contact MAV for a free consultation.
What Clients Say About MAV Design & Build
Verified Google reviews from MAV ADU clients · read all reviews on Google
“I had a great experience with Mav building my ADU. The entire process was smooth, professional, and much easier than I expected. Their team was responsive, transparent, and kept me informed every step of the way.”
“Just completed my ADU with MAV great experience from start to finish highly recommend working with shon very professional”
Ready to Start Your ADU Construction Project in Dickinson?
Free in-home consultation and 3D design preview. Serving Dickinson and the Galveston Bay Area area.
Get Your Free Estimate →Start Your ADU Construction Project in Dickinson Today
Free in-home consultation and 3D design preview. No obligation.
Licensed & Insured · Galveston County · Free Estimates · 3D Design Included
I'm extremely satisfied with my kitchen renovation. The entire process was handled with professionalism and precision. The crew was respectful, efficient, and always made sure I was informed every step of the way. The final result — a beautiful, well-designed kitchen with top-quality finishes and excellent craftsmanship.
Love their work, the kitchen turned out amazing and exceeded our expectations. Completed in much shorter time than I thought it would. Can't recommend them enough!!
Great experience working with this company! They remodeled my kitchen and did an amazing job. The team was professional, easy to work with, and always on time. Everything went smoothly, and they paid attention to the small details.