Houston has no zoning, but Chapter 42 of its Code of Ordinances still sets real rules for what the City calls a “secondary dwelling unit.” Here is what that ordinance actually says — size cap, parking, setbacks, permits and deed restrictions — quoted directly, with the specifics that couldn’t be verified removed rather than repeated.
Book an ADU ConsultationCall (832) 532-6829
Sources: City of Houston Livable Places User Guide (PDF), §2.1 Second Dwelling Unit Concepts (current 1,500 sq ft size cap and unit-size-based parking rule); Houston Code of Ordinances, Chapter 42, Secs. 42-1 & 42-187 (the City’s posted full-chapter redline mixes superseded and current text with no visual distinction once flattened, so the User Guide is used for the current figures); Houston Permitting Center, Residential Addition Permit. Checked Nov. 4, 2026.
What Houston actually calls an ADU
Houston’s Code of Ordinances never uses the term “ADU.” Chapter 42 calls it a secondary dwelling unit. In September 2023, City Council approved the “Livable Places” package of amendments to Chapters 42 and 26 — effective November 27, 2023 — which, in the City’s own words, “allows this housing type to be larger and parking based on the unit size where deed restrictions do not prohibit their construction.” That single sentence is the starting point for almost everything below.
Pick the option closest to your situation:
General guidance based on the City of Houston sources cited throughout this page — not a permit determination for your specific address.
Detached, attached, or a garage ADU
Chapter 42 treats all three the same way for size and parking purposes; the build itself differs.
- 1Best fitA separate, freestanding unitFull privacy, its own entrance, no shared walls. Subject to the same 1,500-sq-ft secondary-dwelling-unit cap and building-line rules as any accessory structure. See MAV’s detached ADU page.
- 1Best fitAn addition with its own entranceConnected to the main house but with independent access. Utility runs from the existing house are typically shorter. See MAV’s attached ADU page.
- 1Best fitReusing an existing structureConverting an existing garage reuses the foundation, walls and roof already in place. This is the one path where MAV has a published, sourced cost guide — see MAV’s Garage Conversion to ADU guide and cost breakdown. See also MAV’s garage ADU page.
What Chapter 42 actually says
Rather than paraphrase, here is what the City’s own ordinance text says, quoted directly. Access note: houstontx.gov and houstonpermittingcenter.org block automated fetches; every quote below was independently confirmed via the Wayback Machine capture cited.
| Topic | What the ordinance says | Source |
|---|---|---|
| Terminology | “Second Dwelling Unit” (Chapter 42’s own legal term is “secondary dwelling unit”) — “Allows this housing type to be larger and parking based on the unit size where deed restrictions do not prohibit their construction.” | Houston Planning & Development, Livable Places |
| Size cap | “A lot upon which is located a free-standing building containing one dwelling unit and a detached secondary dwelling unit of not more than 1,500 square feet also shall be considered single-family residential.” | Chapter 42, Sec. 42-1, Definitions |
| Minimum lot size (platting a new lot only) | 3,500 sq ft in the urban area within the city; 5,000 sq ft in the suburban area and the ETJ; as low as 1,400 sq ft under compensating open-space/averaging performance standards. | Chapter 42, Secs. 42-182 & 42-183 (formerly 42-181) |
| Setbacks (“building lines”) | A front building line varying by street type (roughly 10–25 ft on most single-family streets; less with specific plat standards). “Where deed restrictions provide for a greater building line or setback, the deed restrictions shall control.” No general side/rear setback figure for an accessory or secondary dwelling unit appears in this division. | Chapter 42, Secs. 42-150–42-159 |
| Height | No height limit specific to a secondary dwelling unit appears anywhere in Chapter 42. | Chapter 42 (reviewed in full; not found) |
| Parking | At least two off-street parking spaces per dwelling unit on each lot — except that, per the City’s Livable Places User Guide, parking for a secondary dwelling unit is based on unit size: one additional off-street parking space is required only if the unit is between 1,001 and 1,500 gross square feet, or if the main house itself does not meet its own parking requirement. A unit of 1,000 square feet or less needs no additional space. | Chapter 42, Sec. 42-187 (formerly 42-186) |
| Utility metering | No ordinance requirement for a separate meter. “Small domestic water meters…may service a permanent structure that can be for residential…use” — a separate meter is optional, applied for, not mandated. | Houston Permitting Center, Water Meters |
| Floodplain | Lots without wastewater service “platted in a special flood hazard area, as determined under the National Flood Insurance Program, shall meet the applicable requirements” of the state, city and county. Chapter 19 (“Flood Plain”) separately adopts FEMA’s Special Flood Hazard Areas. | Chapter 42, Sec. 42-181; Chapter 19, Flood Plain |
| Deed restrictions | “The City of Houston is not zoned” — the City has no authority to override active, private deed restrictions, which vary by subdivision and sometimes by section or lot. | City of Houston Legal Department, Deed Restrictions FAQ |
Note: the table above covers Houston’s water-meter rule for an ADU. A separate electric meter is a related but distinct question — mainly relevant if you want the ADU to qualify for its own street address, or want a tenant billed independently. See MAV’s guide, Secondary Electric Meter & Utility Separation for a Houston ADU.
+View as table
| Item | Value (space(s)) |
|---|---|
| Secondary dwelling unit 1,001–1,500 sq ft (additional space) | 1 |
| General rule, per dwelling unit on the lot | 2 |
Source: Chapter 42, Sec. 42-187 (formerly Sec. 42-186), Parking for single-family residential uses. Checked Sept. 25, 2026.
Permits: what the Permitting Center actually posts
A ground-up ADU and a conversion of existing space use different permit types.
| Project type | Permit | Posted processing time |
|---|---|---|
| New accessory structure (ground-up detached/attached ADU) | Residential Addition Permit (HPWCODE1134) | 10 business days |
| Conversion of an existing structure (e.g., garage) | Residential Remodel Permit (HPWCODE1135) | 1–15 business days |
Both sit alongside separate Electrical, Plumbing and Mechanical trade permits once a kitchen, bathroom and HVAC are added — every ADU needs all four. These are the City’s posted plan-review windows, not a full project timeline; revisions, inspections and scheduling can add time. See MAV’s Houston home remodeling permits guide for how permitting works across project types.
What actually drives ADU cost
MAV has not published a cost guide for a ground-up ADU, so this section describes cost drivers rather than a number we can’t source.
If an existing garage is on the table, converting it is the one path MAV has published, sourced figures for: MAV’s Garage Conversion Cost Guide ($18,000–$130,000 depending on scope). For ground-up construction, MAV provides a project-specific estimate after reviewing the lot.
Real MAV ADU projects in the Houston area






Tick each one off as your contractor answers it.
Sources: Harris County Clerk, City of Houston Planning & Development, and Houston Permitting Center (all linked above and in Sources below).
Omer Ahmed and Sam Nogroski’s reviews are about their ADU projects with MAV; the others are verified Google reviews across our services.
“I had a great experience with Mav building my ADU. The entire process was smooth, professional, and much easier than I expected. Their team was responsive, transparent, and kept me informed every step of the way.”
“Just completed my ADU with MAV great experience from start to finish highly recommend working with shon very professional”
“I had a great experience working with this company. From start to finish, the team was professional, reliable, and easy to communicate with.”
“They were easy to communicate with, showed up on time, and made sure everything was done properly.”
“MAV Design & Build did an excellent job with our remodeling project. The team was professional, responsive, and paid close attention to the details.”
About MAV Design & Build
Frequently asked questions
What does Houston actually call an ADU?+
How big can a secondary dwelling unit (ADU) be in Houston?+
Is there a minimum lot size to build an ADU in Houston?+
What are the setback rules for a Houston ADU?+
Does Houston limit ADU height?+
How many parking spaces does an ADU need in Houston?+
Do I need a separate water meter for an ADU?+
Can an HOA or deed restrictions block an ADU even if the City allows it?+
Thinking about a secondary dwelling unit?
Talk through your lot, Houston’s actual Chapter 42 rules, and a realistic plan before you sign a contract.
Book an ADU ConsultationCall (832) 532-6829MAV’s ADU construction services cover detached, attached and garage ADUs, including a detached ADU and a full garage conversion to ADU path with its own sourced cost guide. For how Houston permitting works across project types, see MAV’s home remodeling permits guide.
- City of Houston Planning & Development: Livable Places (Chapter 42 & 26 Development Incentives)
- City of Houston: Chapter 42 Ordinance, full redline text (Livable Places amendments)
- City of Houston Planning & Development: Livable Places User Guide (PDF) — current 1,500 sq ft SDU size cap and parking rule
- City of Houston Planning & Development: Revised Livable Places FAQ (PDF)
- Houston Permitting Center: Residential Addition Permit (HPWCODE1134)
- Houston Permitting Center: Residential Remodel Permit (HPWCODE1135)
- Houston Permitting Center: Water Meters
- Houston Code of Ordinances: Chapter 19, Flood Plain
- City of Houston Legal Department: Deed Restrictions, Frequently Asked Questions
- Harris County Clerk’s Office: Real Property Records
- MAV Design & Build: Garage Conversion Cost in Houston TX, Complete 2026 Guide
All facts above were checked against these sources on September 25, 2026. Houstontx.gov and houstonpermittingcenter.org block automated fetches from this tool; every page cited above was independently confirmed via a Wayback Machine capture on the date noted in research.md. Where a fact could not be confirmed on a primary source — lot coverage percentage, a specific side/rear setback, and an ADU height limit — it was removed from this article rather than restated or estimated.