How to Compare ADU Estimates and Read the Contract
Three ADU bids can be far apart on price because they quietly describe different projects. This guide covers how to line them up, what is most often left out, how to judge a prefab price against a turnkey quote, and the Texas rules on disclosures, retainage and final payment.
Share of the contract price or work value a Texas owner must reserve during the work, and for 30 days after completion (§53.101).
4 items
What Texas’s required disclosure tells owners to get in writing: scope, timing, cost, and payment method (§53.255).
15 days
Deadline for a contractor to update the subcontractor and supplier list after a change (§53.256).
Source: Texas Property Code §§53.101, 53.255, 53.256 (statute text via public.law mirror). Checked Oct. 25, 2026.
The short answer compare scopes, not totals
Two ADU estimates are only comparable once they cover the same scope. Before looking at totals, list every line item from every bid, including design, permits, site work, utilities, foundation, construction, finishes, allowances and final inspection. Mark each as included, excluded or an allowance. Then ask each contractor to price their gaps in writing. The contract should match that scope, follow the Texas disclosure rules, and tie payments to completed work.
Line item
What a complete estimate states
Question to ask
Survey & design
Survey, floor plans, site plan, structural/foundation engineering
Who provides the survey and the engineer’s seal?
Permits & fees
Which permits, who applies, which fees are included
Are permit and impact fees in the price, or passed through at cost?
Site work
Clearing, tree work, grading, drainage, access, restoring fences or driveways
How will equipment reach the backyard, and who repairs what it disturbs?
Utilities
Sewer or septic, water, electric service and meter, gas, internet conduit
How far is each connection, and is a panel or service upgrade included?
Foundation & shell
Foundation type, framing, roof, windows, exterior cladding
Illustration. The documents that let every contractor price the same project: survey, deed restrictions, utility locations, photos and measurements, and your budget and intended use.
Documents to collect first
Tick each one off as your contractor answers it.
One ADU-specific line item: parking
Inside the City of Houston, the size of the ADU can add a parking space to the site work, so check that each estimate prices the same driveway or parking pad.
Extra off-street parking Houston requires for a second dwelling unit+View as table
Item
Value (space(s))
Up to 1,000 sq ft (main house meets its parking)
0
1,001 to 1,500 sq ft
1
Source: City of Houston Livable Places User Guide, Second Dwelling Unit Concepts (§42-186, 188, 188.5): one additional space if the unit is 1,001–1,500 sq ft, or if the main house does not meet its own parking requirement. Checked Oct. 25, 2026.
Interactive check
Why are your estimates so far apart?
Which of these is true of the lowest estimate?
It is probably not the same project. Ask for sewer, water, electric and site work to be priced in writing. These are often among the larger ADU line items.
Low allowances make a total look smaller. Compare each allowance to what you actually plan to choose, and ask what happens if you go over.
Someone still has to pay for and manage those. Ask who applies for the permit; you shouldn’t have to take on the contractor’s permitting.
Then compare schedule, payment terms, warranty, licensed trades and references, and ask to see completed ADUs. Price is one factor among several.
Prefab price vs. turnkey quote
MAV builds site-built ADUs and doesn’t sell prefab, modular, panelized, manufactured or shipping-container units. This section is here so you can compare fairly, whichever route you take.
Illustration. A prefab or modular unit price may cover only the factory-built unit. A turnkey quote should cover everything needed to move in. Ask which items are included before comparing.
To compare a factory-built ADU with a site-built turnkey quote, add everything the unit price leaves out: delivery and crane access, the foundation, utility connections, permits and engineering, site work and drainage, and the steps, decks or flatwork that make it usable. Then compare both on schedule, warranty, and who is responsible if an inspection fails.
A tiny house on wheels is a different product altogether: it isn’t a permanent structure, and area jurisdictions that regulate ADUs generally don’t treat a wheeled unit as a dwelling unit — the City of Galveston’s code, for example, excludes a manufactured home, RV, travel trailer or camper from its ADU rule outright. Check who permits ADUs in your neighborhood before assuming a wheeled unit qualifies.
Texas rules your contract should follow
The same Texas protections apply to any residential construction contract. MAV’s home addition proposal & contract guide covers them in full, including statutory lien waivers. The short version for an ADU:
Disclosure before signing (§53.255)
For a residential construction contract, the contractor must deliver a disclosure statement before you sign. Among other things it says conveying your property to the contractor is not required, tells you to get scope, timing, cost and payment method in writing, and explains subcontractor and supplier lien rights.
Subcontractor & supplier list (§53.256)
Before construction starts, the contractor provides a written list of the subcontractors and suppliers it intends to use, and updates it within 15 days of any change unless you waive updates.
10% retainage (§53.101)
Reserve 10% of the contract price, or of the value of work done, during the work and for 30 days after completion. Payments released early can leave you exposed to lien claims from unpaid subcontractors.
Final bills-paid affidavit (§53.259)
At final payment, the contractor signs an affidavit that everyone has been paid in full, or lists who is still owed. A false affidavit is a misdemeanor, and the signer is personally liable for resulting losses.
Illustration. An example milestone schedule: each payment follows completed, inspected work, with 10% held back through completion plus 30 days.
Financing the ADU against your homestead adds separate constitutional rules (waiting periods, closing location, spouse consent). See ADU financing in Texas.
Warning signs in an ADU contract
Vague scope
“Build ADU per plans” with no line items, allowances or exclusions.
Payments ahead of work
Large payments tied to dates instead of completed, inspected milestones, with no retainage.
No disclosure or sub list
No §53.255 disclosure before signing, or no subcontractor and supplier list before work starts.
Asks for your title
Any request to convey your property to the contractor. The required Texas disclosure states it isn’t required.
You pull the permit
Pressure to apply for the permit in your own name for work the contractor is performing.
Unverifiable trades or insurance
No license numbers for the electrician, plumber or HVAC contractor, and no certificate of insurance from the insurer or agent.
Appliances, laundry, tile, plumbing fixtures and vanities. Each is a line item or an allowance that should be spelled out in an ADU estimate.
Appliance package: each one is a line itemLaundry hookups and appliancesTile, wallpaper and fixtures: finish allowancesPlumbing fixture selectionsShower glass, tile and vanityTile niche detailShower valve and trimBath finishes: tile, vanity, lightingTile scope runs floor to ceilingCabinets, backsplash and an exposed beam
More from MAV ADU projects (19 photos)
Bathroom vanity and glass showerWalk-in shower with three tiled nichesRow of tiled shower nichesThree recessed niches with hexagon mosaicShower valve and slide barSmall bath vanity beside the hallwaySingle vanity with mirror and towel ringGlass shower with framed tile nichesShower, toilet and vanity in a compact bathVanity with barn-door cabinetLarge-format tile shower wallShower wall with black fixtures and a shelfBrass slide bar and tiled niche on hexagon tileShower fixtures beside a glass panelBrass handheld shower and valve trimBath with dark vanity and glass showerVanity, shower glass and hallway viewClose view of patterned cement-look tileTiled shower with a window
Photos of completed MAV Design & Build projects. Project addresses and locations are not shown, to protect homeowners’ privacy.
Watch: From drawing to design concept
From drawing to design concept
A hand-drawn remodel plan becomes an AI-assisted design concept (the clip carries a “Veo” watermark), followed by layout and connection diagrams and finished-space concepts. On-screen text: “The drawing has” · “That line is” · “That opening changes” · “That corner might” · “A design concept” · “Understand the space” · “Plan and” · “Ask the questions” · “Taking shape” · “And build”. End card: “Let’s make your project idea easier to understand.”
22 seconds · tap to play (nothing loads until you do).
MAV Design & Build video. Scenes are labelled in the video as design concepts, illustrations or supplied project footage; it is not presented as one specific completed project.
What MAV clients say on Google5.0on Google
The first two reviews are from MAV ADU clients. The third is from a client of another MAV service, about pricing honesty.
“I had a great experience with Mav building my ADU. The entire process was smooth, professional, and much easier than I expected. Their team was responsive, transparent, and kept me informed every step of the way.”
“Just completed my ADU with MAV great experience from start to finish highly recommend working with shon very professional”
“They were honest about pricing, communicated well, and delivered exactly what they promised.”
At minimum, the four items Texas law tells owners to get in writing (Tex. Prop. Code §53.255): a description of the work, the required or estimated completion time, the cost or how it will be determined, and the payment procedure. For an ADU, the description should also list design and engineering, permits, site work and drainage, utility connections (sewer or septic, water, electric, gas), foundation, construction, finishes, allowances, and final inspection or certificate of occupancy.
How do I compare ADU estimates with different scopes?+
Build one list of every line item from all the estimates. Mark each one as included, excluded or an allowance in each estimate, and price the gaps with the contractors before comparing totals. The estimate that includes utilities, site work and permits will look higher than one that leaves them out, but it may be the lower final cost.
What costs are usually excluded from ADU estimates?+
The items most often left vague or out are the property survey, engineering, permit and impact fees, utility extensions and connections (especially sewer distance and electric service upgrades), drainage and grading, tree work, restoring fences or driveways after access, and finish selections above the allowance. Ask about each in writing.
What is a reasonable construction payment schedule?+
One where each payment follows completed, inspected work rather than getting ahead of it, and lines up with your lender’s draw schedule if you’re financing. Texas law requires the owner to reserve 10% of the contract price or of the work’s value during the work and for 30 days after completion (Tex. Prop. Code §53.101). That reserve protects you against subcontractor and supplier lien claims.
How should allowances and change orders be handled?+
Each allowance should name the item, the dollar amount and what happens if you choose something above or below it. Every change order should be in writing, signed before the work, and show the price and schedule effect. Verbal changes are the most common source of end-of-job disputes.
Does Texas license general contractors?+
Texas has no state general-contractor license. The Texas Department of Licensing and Regulation licenses electricians and air-conditioning contractors, and the Texas State Board of Plumbing Examiners licenses plumbers. Both have public license lookups. Ask which licensed trades will do that work on your ADU, and verify their numbers.
What should I receive at the end of the job?+
The final inspection or certificate of occupancy from your permitting authority, warranty terms in writing, and a final bills-paid affidavit. Texas requires the original contractor to deliver that affidavit when final payment is tendered, stating everyone has been paid in full or listing anyone still owed (Tex. Prop. Code §53.259).
What is the difference between an ADU and a tiny home?+
Mostly permitting, not size. A “tiny home” usually means a small, often trailer-built structure sold as a standalone product, and a trailer-built unit can be classified as an RV rather than a permanent dwelling in some jurisdictions. An ADU, as MAV builds it, is a site-built, permitted secondary dwelling unit reviewed under your specific lot’s zoning, building code and utility rules — the same review this checklist and MAV’s neighborhood-by-neighborhood permitting guide walk through. Whether a trailer-built unit would even qualify for a building permit as a dwelling varies by jurisdiction; confirm directly with your permitting office if that is what you’re comparing against a site-built ADU.
Why do small ADUs cost more per square foot than larger ones?+
A kitchen, bathroom, utility connections and a foundation cost close to the same whether the unit is 400 sq ft or 1,000 sq ft, so that fixed cost is spread over fewer square feet in a smaller unit. That is why MAV prices an ADU by finish scope — studio or home office, guest suite with a bath, or full apartment with a kitchen — rather than by a flat per-square-foot rate. Ask MAV to price your specific scope instead of comparing projects on $/sq ft alone.
How does heavy rain affect the construction schedule?+
Houston’s wettest stretches — spring, and hurricane season from roughly June through November — are a real source of delay for the exterior-facing phases: foundation, framing and roofing. Before you sign, ask in writing how your contract treats a weather delay: whether the completion date moves and whether the fixed price stays fixed either way. Get that answer from the contract, not a verbal assurance.
Get an estimate you can compare line by line
MAV prices ADUs as a fixed scope covering design, permits, site work, utilities and construction, with allowances and exclusions written out.
Checked October 25, 2026. Statute text read via the public.law mirror (the Legislature’s own site does not render to automated readers). A summary, not legal advice.
What Houston Homeowners Say⭐ 5.0 • Google Reviews
Waseem NaqviApril 2026
★★★★★
I'm extremely satisfied with my kitchen renovation. The entire process was handled with professionalism and precision. The crew was respectful, efficient, and always made sure I was informed every step of the way. The final result — a beautiful, well-designed kitchen with top-quality finishes and excellent craftsmanship.
AviadApril 2026
★★★★★
Love their work, the kitchen turned out amazing and exceeded our expectations. Completed in much shorter time than I thought it would. Can't recommend them enough!!
Dwight HoldenMarch 2026
★★★★★
Great experience working with this company! They remodeled my kitchen and did an amazing job. The team was professional, easy to work with, and always on time. Everything went smoothly, and they paid attention to the small details.