Compare the scope line by line before you compare prices. Three bids for the same addition can differ by tens of thousands of dollars because one includes engineering, permits, the roof tie-in and finishes and another doesn’t. Then check the Texas protections every residential contract should come with: the disclosure statement, subcontractor list, 10% reserve and lien waivers.
Request a Free EstimateCall (832) 532-6829Illustration. Same room, three prices — the cheapest proposal usually names the fewest line items.
Sources: Texas Property Code §§53.101, 53.255, 53.256, 53.284 as amended by HB 2237 (87th Leg., effective Jan. 1, 2022). Checked Oct. 25, 2026. This guide is general information, not legal advice.
A complete proposal follows the same path as the project: the first conversation, design decisions, construction stages and the final walkthrough.
What the video shows: A 27-second MAV Design & Build reel walking through the stages a proposal should cover — the first conversation, layout concepts, framing and the final walkthrough. Burned-in captions; scenes are labelled in the video as supplied project footage, design concepts and illustrations.
What should a room addition proposal include?
A complete addition proposal names every phase from drawings to final inspection, says who is responsible for each, and states whether each item is a fixed price or an allowance. If an item is missing, the proposal isn’t cheaper — the cost has just moved to a change order, to you, or to nobody until it becomes a problem.
| Line item | What a complete proposal says | Red flag if you see |
|---|---|---|
| Design & drawings | Who produces plans, how many revisions, and whether a 3D model is included | Plans “by owner” or not mentioned |
| Engineering | Structural review/stamped design where needed; foundation and framing | No mention on a second-story, over-garage or wall-opening job |
| Survey & site checks | Boundary survey, setbacks, easements, deed restrictions/HOA review | Assumes your lot can take the footprint |
| Permits & fees | Who applies, which office, and whether fees are in the price | Permit “if required” or “not included” |
| Demolition & site prep | Opening the exterior wall, removals, haul-off, protection of the existing house | No protection or dust plan for an occupied home |
| Foundation | Type, size, how it ties to the existing house; soils assumption | One lump sum with no description |
| Framing & roof tie-in | Walls, floor/roof system, how the new roof meets the old one, weatherproofing | Roof tie-in not described |
| Exterior match | Brick/siding, roofing, windows matched to the house — or not | Silent on matching materials |
| Mechanical, electrical, plumbing | HVAC approach, panel capacity, circuits, plumbing runs for any bathroom | “Extend existing” with no capacity check |
| Insulation & finishes | Insulation, drywall, flooring, trim, paint, doors, fixtures — fixed or allowance | Finishes only as vague allowances |
| Inspections & close-out | Final inspection, as-builts, warranty documents, lien releases at the end | Nothing after “substantial completion” |
A planning list for comparing proposals — not an exhaustive scope for every project. Your project may add items (a bathroom, a balcony, a stair) or drop some.

Specialty tile and brass fixtures: a fixed selection or an allowance? The proposal should say which.

Stone tile, glass and a linear drain — details to see priced in writing before you sign.

Appliance packages vary widely in price; compare the model or allowance each bid carries.
Why prices differ: the usual missing pieces
For how MAV’s published cost ranges are built, see the home addition cost guide and room addition cost guide. For who does what under each delivery model, see design-build vs. general contractor.

A finished kitchen — the end state a complete proposal should describe line by line.
This is the end state a proposal should describe. Every surface in a finished room — cabinets, counters, tile, flooring, fixtures, lighting — is either a named, priced selection or an allowance. Ask each bidder to show which is which.
Even a compact kitchen carries a dozen separate selections. When one bid lists them and another says “kitchen per plan,” you are not comparing the same thing.

Even a compact kitchen has a dozen selections: cabinets, counters, tile, sink, faucet and appliances.
Allowances, selections and change orders

Vanities, faucets and lighting are finish selections that move a final price up or down.




For each allowance ask: what product or quality level the number assumes, whether it includes installation, and how the difference is billed (cost plus markup, or at cost). A list of allowance assumptions turns a vague number into something you can compare between proposals.
Selections that are made before the contract is signed can be priced as fixed items. Late selections can delay ordering and the schedule — ask for a selections deadline list tied to the construction sequence.
Every change — yours, or one forced by a hidden condition — should be written before the work is done: description, price or credit, schedule effect, and both signatures. Ask how hidden conditions found when the wall is opened will be documented, with photos, before work continues.
Some homeowners keep a contingency outside the contract for unknowns; some proposals carry one inside. Either way, it should be visible and its use documented by change order, not absorbed silently. How large it should be depends on the age and condition of the house — older homes justify more.
Texas protections that come with every residential contract
Texas Property Code Chapter 53 gives homeowners specific documents and tools. Knowing them makes it easy to spot a contract that skips them.
+View as table
| Item | Value (days) |
|---|---|
| Updated sub/supplier list after a change (§53.256) | 15 |
| Reserve kept after completion (§53.101) | 30 |
| Homestead renovation lien: credit wait | 5 |
| Homestead renovation lien: rescission | 3 |
Source: Texas Property Code §§53.101, 53.256 (statute text; HB 2237 enrolled text); Texas Constitution Art. XVI §50(a)(5)(B)–(C) (Texas Legislative Council). Whether the constitutional conditions apply to a specific contract is a question for a lender or Texas attorney. Checked Oct. 25, 2026.
Two more items to look for on an existing-home project: Property Code §41.007 requires a contract for improvements to an existing residence to carry a bold “IMPORTANT NOTICE” warning that you may lose ownership rights if you don’t meet the contract’s terms, and requires any binding-arbitration clause to be in at least 10-point bold type to be enforceable against the owner. If your contract has neither, ask why.
General information from the statutes cited, not legal advice. For how a statute applies to your contract or financing, consult a Texas attorney.
Payment schedules tied to completed work
Pay for work that is complete and checkable — a passed inspection, framing you can see — not for dates on a calendar. A schedule like this keeps your payments in step with the value in place and gives each payment a clear trigger. Pair each progress payment with a conditional waiver from the contractor (and from major subcontractors and suppliers where you choose), then the unconditional version once the payment has cleared.
If you’re financing the addition, your lender may set its own draw schedule and inspections — MAV’s remodeling financing guide explains the common options.
Pick what you’re seeing in the bids you have:
Tick each one off as your contractor answers it.
A homeowner checklist; not legal advice.
MAV’s verified review set does not yet include a room-addition project. These verified Google reviews mention pricing honesty, communication and transparency across MAV’s projects.
“I had a great experience with Mav building my ADU. The entire process was smooth, professional, and much easier than I expected. Their team was responsive, transparent, and kept me informed every step of the way.”
“The team was easy to work with, communicated well throughout the project, and paid attention to the small details.”
“They took the time to understand what I wanted and offered helpful suggestions without being pushy.”
“They were honest about pricing, communicated well, and delivered exactly what they promised.”
About MAV Design & Build
Frequently asked questions
Why is one contractor’s addition quote so much lower than the others?+
What does Texas law require my contractor to give me before I sign?+
What is the 10% I’m supposed to hold back?+
Which lien waivers should I collect?+
Is there a legal limit on how much deposit a Texas contractor can ask for?+
Do I need to sign the contract at a title company or wait five days?+
How should change orders be handled?+
What should I get at the end of the project?+
Offer shown in the video: design cost credited back.
Terms, eligibility and how long the offer runs are confirmed by MAV in writing before you sign — ask when you request your estimate. What the video shows: A 35-second MAV Design & Build promotional video on planning with architectural-level floor plans and 3D design before construction — so the proposal you compare describes a defined project.
Ask About This OfferCall (832) 532-6829Related room-addition planning guides
Want a proposal you can compare line by line?
Tell MAV what you want to add. We’ll walk you through the scope — drawings, engineering, permits, the connection to your house and finishes — and give you a free estimate.
Request a Free EstimateCall (832) 532-6829Related MAV pages: Room Additions, Room additions by city, Master Suite Addition, home addition cost guide, design-build vs. general contractor, remodeling financing, home additions planning & permits and final inspection & certificate of occupancy.
- Texas Property Code §53.255 — disclosure statement for residential construction contracts
- Texas Property Code §53.256 — list of subcontractors and suppliers
- Texas Property Code §53.101 — funds required to be reserved (formerly “retainage”)
- HB 2237, 87th Legislature (enrolled) — Chapter 53 amendments effective Jan. 1, 2022
- Texas Property Code §53.283 — unconditional waiver requires payment
- Texas Property Code §53.284 — statutory lien waiver and release forms
- Texas Property Code §41.007 — home improvement contract notice and arbitration clause
- Texas Constitution Art. XVI §50(a)(5) — homestead liens for improvements (Texas Legislative Council)
The official statutes site renders statute text only in a browser app, so section text was taken from verbatim statute reproductions and checked against the enrolled HB 2237 text for the 2022 changes (terminology “retainage” → “reserved funds”; lien-waiver notarization removed). No statutory deposit cap was found in the sections reviewed; that is a limited search result, not a legal conclusion. Checked October 25, 2026. Not legal advice.
I'm extremely satisfied with my kitchen renovation. The entire process was handled with professionalism and precision. The crew was respectful, efficient, and always made sure I was informed every step of the way. The final result — a beautiful, well-designed kitchen with top-quality finishes and excellent craftsmanship.
Love their work, the kitchen turned out amazing and exceeded our expectations. Completed in much shorter time than I thought it would. Can't recommend them enough!!
Great experience working with this company! They remodeled my kitchen and did an amazing job. The team was professional, easy to work with, and always on time. Everything went smoothly, and they paid attention to the small details.